Piluwa Khola Small Hydropower Project is a Run-of-River Hydroelectricity power plant developed by Arun Valley Hydropower Development Co. Ltd. Located in Sankhuwasava district. It has an installed capacity of 3 MW and has a net annual generation amount of 19.547 GWhr.
Design Discharge | 3.5 m3/s |
---|---|
Maximum Gross Head | 112.5m |
Diversion Length | 21m |
---|
Penstock- Length | 3km |
---|---|
Penstock-Diameter | 1620mm dia, 8-14mm |
Power House | Surface, 19.10 x 8.50 m with indoor switchyard |
---|
Type | Turgo Impulse |
---|---|
Number of Units | 2 |
Rated Capacity | 1721 Kw |
Number of Generators | 2 |
---|---|
Rated Capacity | 2000 kVA |