Hydropower Projects

mai khola

Upper Myagdi Hydroelectric Project

Marang,Mudi,Muna (Myagdi)

  • Issue Date: 2013-02-20
  • Installed Capacity : 37MW
  • Phase : Under Construction
mai khola

Rupse Khola Hydropower Project

Dana (Myagdi)

  • Issue Date: 2014-04-18
  • Installed Capacity : 4MW
  • Phase : Under Construction
mai khola

Upper Dordi A Hydroelectric Project

Dhodeni,Faleni (Lamjung)

  • Issue Date: 2014-04-28
  • Installed Capacity : 25MW
  • Phase : Live
  • Type : Run Of River
mai khola

Khare Hydropower Project

Chankhu,Khare,Marbu (Dolakha)

  • Issue Date: 2014-05-04
  • Installed Capacity : 24.1MW
  • Phase : Under Construction
  • Type : Run of River
mai khola

Maya Khola Hydropower Project

Mamling,Madi Rambeni,Baneswor (Sankhuwasabha)

The Maya Khola Hydropower Project is a 14.9 MW run-of-river hydroelectric facility located in Sankhuwasabha District, Koshi Province, eastern Nepal. Developed by Maya Khola Hydropower Company Ltd, the project harnesses the flow of the Maya Khola river. Originally planned for 5 MW, the capacity was upgraded under NEA’s Q40 norm. The project was commissioned in December 2019 and is connected to Nepal’s national grid via a 3.4 km, 33 kV line to NEA’s Baneshwar substation, and later integrated into the 220 kV Koshi Corridor on 16 February 2023. The company transitioned from a private limited to a public limited company in May 2016 to facilitate public equity investment. Financing was secured through a consortium loan of NPR 1.825 billion from NIB, Century Bank, and Civil Bank. The project’s generation license, issued on 12 June 2014, is valid for 35 years. An IPO launched in early 2023 split equity with a 66:34 promoter-public ratio. Maya Khola exemplifies a community-inclusive and PPP-type development model, contributing clean energy to Nepal’s growing energy needs.
  • Issue Date: 2014-06-09
  • Installed Capacity : 14.9MW
  • Phase : Live
mai khola

Bagmati Nadi Hydropower Project

Kogate,Ipa Panchakanya,Sisneri Mahadevsthan (Makawanpur)

  • Issue Date: 2014-07-03
  • Installed Capacity : 22MW
  • Phase : Live
mai khola

Solu Khola (Dudha Koshi) Hydropower Project

Kagel,Tingla,Panchan,Newa Beddhari,Salyan (Solukhumbu)

  • Issue Date: 2014-09-18
  • Installed Capacity : 86MW
  • Phase : Live
  • Type : Run Of River
mai khola

Sabha Khola A Hydropower Project

Dhupu,Syabun (Sankhuwasabha)

  • Issue Date: 2014-10-12
  • Installed Capacity : 8.3MW
  • Phase : Under Construction
mai khola

Lower Midim Khola Small Hydropower Project

Karapu (Lamjung)

  • Issue Date: 2014-11-05
  • Installed Capacity : 0.996MW
  • Phase : Under Construction
mai khola

Badigad Hydropower Project

Burtiwang,Bhinggithe,Rajkut (Baglung)

  • Issue Date: 2015-01-01
  • Installed Capacity : 6.6MW
  • Phase : Under Construction
mai khola

Durbang Myagdi Khola Hydropower Projcet

Arman,Babiyachaur,Devisthan,Darwang,Niskot (Myagdi)

  • Issue Date: 2015-02-16
  • Installed Capacity : 25MW
  • Phase : Under Construction
mai khola

Upper Khimti II Hydropower Project

Chuchure (Ramechhap)

  • Issue Date: 2015-05-27
  • Installed Capacity : 7MW
  • Phase : Live